JOB-2026-0422

Scheduled

Hydrant Marker Post 1.2m

Hydrant Australia

Live margin

36.7%

$1,980 on $5,400

Marker-post stock below reorder — PO-2026-074 raised.

Progress

Quoted
Scheduled
Tooling
Moulding
Profiling
Finishing
QA
Dispatched
Invoiced

Costing

Sell (ex-GST)
$5,400
Production cost
$3,420
Margin
$1,980 · 36.7%
GST (10%)
$540
Invoice total (inc-GST)
$5,940.00

Linked records

Work order — routing

  1. Scheduled in progress
  2. Tooling
  3. Moulding
  4. Finishing
  5. QA
  6. Dispatched
Produced0 / 120 ea

Material & tooling

Resin
Polyethylene (PE)
Shot weight
4,750 g × 1 cav
Resin required
570.0 kg
Material cost
$1,539.60
Shots (≈)
120 @ 26s
Mould tool