STE
BC

Brad Coleman

Group Owner · Executive

Layout

Settings
Xero connectedLast sync 2026-06-24 09:14 AEST
STE Stile Edge BC
← Job book

JOB-2026-0413

Finishing

Cable Saddle 25mm

B&K Plastics

Live margin

25.0%

$1,500 on $6,000

Progress

Quoted
Scheduled
Tooling
Moulding
Profiling
Finishing
QA
Dispatched
Invoiced

Costing

Sell (ex-GST)
$6,000
Production cost
$4,500
Margin
$1,500 · 25.0%
GST (10%)
$600
Invoice total (inc-GST)
$6,600.00

Linked records

  • CustomerReece Group
  • Quantity50,000 ea
  • PartBK-2062
  • Quote
  • Invoicenot yet raised
  • Machine
  • OperatorMoulding Supervisor
  • Due26 June 2026

Work order — routing

  1. Scheduled
  2. Tooling
  3. Moulding
  4. Finishing in progress
  5. QA
  6. Dispatched
Produced50,000 / 50,000 ea

Material & tooling

Resin
Nylon 66 (PA66)
Shot weight
6 g × 7 cav
Resin required
300.0 kg
Material cost
$2,000
Shots (≈)
7,143 @ 52s
Mould tool
MT-238